TCN Plans 10-Hour Power Outage in Kubwa, Zuba, Bwari and Four Other Abuja Areas

By —

The Transmission Company of Nigeria (TCN) will shut down power supply to parts of Abuja for 10 hours on Saturday, November 28, 2026, to allow its maintenance crew work at the Katampe Transmission Substation.

The outage will run from 8:00 a.m. to 6:00 p.m., TCN said in a statement published on its official X account on Saturday.

What the maintenance involves

TCN said the crew will work at the 330/132/33kV Katampe Transmission Substation to reconnect jumpered conductors to a newly installed 330kV incomer line disconnector switch with an earthing switch.

The work will temporarily stop the Abuja Electricity Distribution Company (AEDC) from receiving electricity from the substation for distribution to its customers.

“The Transmission Company of Nigeria (TCN) wishes to inform the public that its maintenance crew will carry out scheduled maintenance at the 330/132/33kV Katampe Transmission Substation on Saturday, November 28, 2026, from 8:00am to 6:00pm,” the statement read.

Areas to be affected

The communities affected include Kubwa, Bwari, Deidei, Zuba, Kaduna Road, Dakwa and Sabon Wuse.

Supply through the substation should resume after the 10-hour window, subject to the completion of the maintenance work.

A repeat of earlier disruptions

This is not the first planned TCN exercise to cut supply in the Federal Capital Territory. In February 2025, the company scheduled preventive maintenance on two 100MVA transformers at the Apo 132/33kV Transmission Substation.

That exercise affected electricity supply to parts of Garki, Area 1, Asokoro, Gudu and surrounding communities. It was scheduled over two days, between 9:00 a.m. and 4:00 p.m. each day, with AEDC unable to receive bulk electricity from the transformers during the period.

The latest outage concerns the Katampe substation, not the Apo facility.

Abuja has also seen unplanned disruptions. On October 19, 2026, AEDC blamed interruptions in several FCT communities on technical faults, while wider supply problems across the country were linked to reduced electricity allocation from the national grid.

The communities affected then included Kado Fish Market, Life Camp Extension, Nizamiye Hospital, Diamond Court Estate, HUS Prime Estate, Decent Creation, Mab Global Estate and Idu Karmo.

AEDC said its technical team was working to resolve the fault, with restoration targeted for 11:00 a.m. on the day of the announcement.

Those October disruptions were caused by technical faults and lower grid allocation. Saturday's interruption is a scheduled maintenance exercise announced by TCN.

Residents in the affected communities should plan around the 8:00 a.m. to 6:00 p.m. window on November 28.

AD Naija Life Game — earn money and grow your business

You can earn money on Naija Life Game and use it to advertise your business and services. Showcase what you offer and connect with potential customers.

Earn money Advertise your business Promote your services Connect with customers

Earn money. Get noticed. Grow your business with Naija Life Game.

Visit Naija Life Game

Forex News

TCN Plans 10-Hour Power Outage in Kubwa, Zuba, Bwari and Four Other Abuja Areas
ABOKI FOREX
FCC Lifts Suspension on Customs Recruitment Training as 2,696 Recruits Continue
ABOKI FOREX
AI will not replace workers who learn to govern it, Olayinka James says
ABOKI FOREX
Kenya Airways Seeks $1.5bn Strategic Investment by Mid-2027
ABOKI FOREX
Nigeria’s economic problems go beyond APC and PDP, Zinnc CEO says ahead of 2027
ABOKI FOREX
Lagos unveils 30+ December 2026 events, targets diaspora and tourists
ABOKI FOREX
Wale Tinubu, Otedola lead NGX billionaire gains as Dangote loses N30.12 billion
ABOKI FOREX
Lagos sinking 5mm yearly as African coastal cities face faster subsidence, study finds
ABOKI FOREX
Senator Idiat Adebule Dies at 56, Creates Lagos West Senate Vacancy
ABOKI FOREX
Lagos opens complaint channels for artisans who abandon jobs, delay delivery
ABOKI FOREX